Installation of a fire network system that includes a machine room and storage tank for a warehouse of 12,000 square meters.
Installation of carbon steel pipes for connection of air conditioning handlers.
Civil and mechanical work for the modification of oil storage tanks in the Sabritas plant.
Replacement of dryer rolls in machine 2 of production line.
Manufacture and installation of stainless steel ducts for forced air.
Supply and installation of galvanized steel pipes, valves and accessories for industrial water pumping equipment.
Supply of installation of pipes, valves, accessories, insulation, support and foundations for the installation of a dual boiler system of 800 cc. in the engine room (steam system).
Assembly and assembly of production line, cold glass, oven 2.
Supply and Installation of stainless steel pipes, valves and accessories for cooling tower supply.
Supply, installation, insulation, support and foundation of pipes, valves and accessories for the installation of a dual electrolyte heating system in the ESME II plant. 1200 cc heaters
Manufacture of hydraulic compensator by ASME code for operating pressure of 6 bar.
Supply, installation, insulation, support and foundation of carbon steel pipes, valves and accessories for the installation of a steam generation system with a capacity of 17 ton / hr at the FEMSA Santa Clara plant.
Supply, installation, insulation, support and foundation of carbon steel pipes, heads, valves and accessories for installation of steam generation system with a capacity of 26 ton / hr and interconnection with the operating system in Yucateca brewery, Grupo Modelo.
Cleaning and descaling of silica in silencers and channels of the geothermal field of Cerro Prieto in the Valley of Mexicali.
Maintenance and modification of distribution lines of 13.2 Kv in the geothermal field of Cerro Prieto in the Mexicali Valley.
Installation of a fire network system that includes a machine room and storage tank for a warehouse of 12,000 square meters.
Installation of carbon steel pipes for connection of air conditioning handlers.
Civil and mechanical work for the modification of oil storage tanks in the Sabritas plant.
Replacement of dryer rolls in machine 2 of production line.
Manufacture and installation of stainless steel ducts for forced air.
Supply and installation of galvanized steel pipes, valves and accessories for industrial water pumping equipment.
Supply of installation of pipes, valves, accessories, insulation, support and foundations for the installation of a dual boiler system of 800 cc. in the engine room (steam system).
Assembly and assembly of production line, cold glass, oven 2.
Supply and Installation of stainless steel pipes, valves and accessories for cooling tower supply.
Supply, installation, insulation, support and foundation of carbon steel pipes, valves and accessories for the installation of a steam generation system with a capacity of 17 ton / hr at the FEMSA Santa Clara plant.